The ReConnect 4 project for Pokalambro Telephone Cooperative involved the construction of approximately 134 miles of long-haul ring fiber infrastructure to expand and strengthen rural broadband connectivity across northwest Texas.

 

Executed under a federally funded grant program with strict milestone deadlines and third-party inspection requirements, the project required sustained high-production rates, disciplined logistics, and consistent quality control across remote terrain.

 

Isbell completed the build in just over 100 days, maintaining schedule integrity and zero recordable incidents while delivering reliable installation and restoration that met rigorous compliance standards.

Back Hoe Angle 2 (1).jpg

Challenges Faced

Rock Trenching Angle 4.jpg

Sustained High-Production Across 134 Miles

The 134-mile long-haul fiber build required disciplined coordination, equipment uptime, and sequenced production to maintain consistent daily progress across rural corridors.

Back Hoe Angle 3 (1).jpg

Strict Federal Funding Milestones & Inspection Oversight

As a federally funded ReConnect project, the build operated under strict milestones, inspections, and documentation requirements with little tolerance for delay or error.

Fiber Cable Plow Angle 1.jpg

Expansive Rural Geography & Access Coordination

The route spanned remote northwest Texas terrain, requiring strategic staging, mobilization planning, and field oversight to maintain efficient progress.

Fiber Cable Plow Angle 3.jpg

High-Production Execution Across 134 Miles

For the 134-mile ReConnect 4 build, Isbell maintained consistent daily production through strategic staging, heavy-capacity equipment, and field support, completing the project in just over 100 days.

Back Hoe Angle 4.jpg

Remote Routing & Access Management

Crews navigated remote access and long rural spans using large-scale plowing, directional drilling, and disciplined coordination, with proactive planning and client alignment preventing delays and ensuring compliance.

Isbell Logo on Equipment.jpg

Federal Milestone Execution

Under strict grant milestones and inspections, Isbell maintained disciplined tracking, self-performed critical scopes, and ensured equipment uptime to deliver steady progress across the 134-mile build without compromising compliance or quality.

Measurable Project Outcomes

100%

0.00

134

100

Schedule Adherence

Project delivered 14 days ahead of federal execution timelines without deviation.

Zero recordable accidents or lost-time incidents across all intensive field hours.

Safety TRIR Score

High-production long-haul fiber placement across remote northwest Texas terrain with disciplined compliance and restoration excellence.

Miles Placed

Installed 134 miles of long-haul fiber at over one mile per day while maintaining schedule discipline, equipment uptime, and full compliance.

Days

Back Hoe Digging Angle 1.jpg

Safety Performance & Operational Assurance

Safety is our primary measure of success, reflected in our industry-leading 0.61 EMR and disciplined risk management.